top of page

Meridian Steps - Stratford Station

Innovative temporary fire escape installation at Stratford Station, enabling future development while maintaining essential emergency evacuation routes.

Scope of Works

The multi-phase construction programme included:


Enabling Works:

  • Site establishment and subway cover slab exposure

  • Installation of PFC hangers to support the structure

  • Casting of in-situ reinforced concrete beams

  • Construction of the canopy steel frame and block work

Main Installation:

  • Precision cutting and removal of the existing cover slab

  • Installation of a Haki modular staircase system

  • Fitting of double emergency fire exit doors

  • Application of cladding with integrated guttering and downpipes

  • Footpath construction and hoarding installation

Services Integration:

  • Relocation and installation of the existing dry riser

  • Application of new line markings

  • Making good exposed walls and ceilings

  • Installation of CCTV systems and fire alarm points

  • Provision of support steel columns and beams

  • Modification of existing services

  • Installation of containment systems, luminaires and emergency lighting

  • Distribution board and cable installations

Location:

July 2024 - April 2025

Project Value:

£118,657.00

Duration:

July 2024 - April 2025

Client:

RG Group

Contract:

The Challenge:

Creating a new emergency escape route through an existing below-ground structure presented significant technical challenges. The works needed to be delivered while maintaining full station operations, with particular attention to ensuring continuous emergency evacuation capabilities throughout. The location within a busy transport hub added complexity to material deliveries and work scheduling.

Our Approach:

Working closely with our design partners at Crayside Consulting, we developed comprehensive Civil & Structural, Electrical and SISS design solutions. Our collaborative approach encompassed detailed assessment of the existing earth-retaining structural mechanisms, design of a roof ‘cut-out’ for the new staircase, creation of an ‘end-wall’ to block the existing escape route, and development of a complete entrance/canopy structure.

Overcoming Challenges:

The project required working in a live station environment while ensuring emergency evacuation routes remained operational throughout. Careful phasing was essential to maintain safety standards at all times. The construction of a new opening through an existing structure while maintaining its structural integrity demanded precise engineering calculations and execution.

Key Achievements:

By creating a temporary Network Rail safe access route and maintaining continuous station operations throughout, we demonstrated our ability to deliver complex infrastructure modifications in live transport environments. The successful completion of this project enabled the subsequent development of significant student accommodation above the station, showcasing our role in supporting urban regeneration while enhancing railway infrastructure.

Previous Item
Next Item
bottom of page